In October, we began construction of our estate winery.
The building site is located on Coopersmith Vineyard, a Pinot Noir property
that my husband Ken and I own and farm. We anticipate moving into Merry
Edwards Winery in time to receive the 2007 harvest. Our small, specialized
facility will be home to my handcrafted, limited production, Russian
River Valley Pinot Noir and Sauvignon Blanc wines. On this page we will
post a diary of our progress. We invite you to share our adventure.
 |
August
24th, 2007
Harvest Team 2007 celebrates Flax Pinot Noir
as the first grapes to christen the new winery! |
| |
|
 |
 |
August 3rd, 2007
The
first truck of case goods moves into the new winery! |
July 11th, 2007
Arrival of the Refrigeration Package on its skid. |
| |
|
 |
 |
July 10, 2007
Grading
the parking lot. |
June 20, 2007
The roof goes on the
tank room (exterior view) |
| |
|
 |
 |
June 20, 2007
The roof
goes on the tank room (interior view) |
June 11, 2007
Tanks view the sky in their new home |
| |
|
 |
 |
June 11, 2007
Settling the first tank into position |
June 11,
2007
Two cranes move tank into place |
| |
|
 |
 |
June 11,
2007
Moving the first tank into building |
June 11,
2007
Our first tank arrives! |
| |
|
 |
 |
May 23rd, 2007
Two Happy
Builders |
May 23rd, 2007
First
demising wall goes up |
| |
|
 |
 |
May 23rd, 2007
Foreground- temporary
solar installation;
background- we look like
a building! |
May 15th, 2007
Side
wall installation nearly complete |
| |
|
 |
 |
May 8th, 2007
Installation
of first API wall panels in tank room. |
April 27th,
2007
All in a day's work |
| |
|
 |
 |
April 27th,
2007
Final roof section goes up |
April 27th,
2007
Basic roof structure completed |
| |
|
 |
 |
April 27th,
2007
Raising section 3 |
April 27th,
2007
Section 4 in place |
| |
|
 |
 |
April 27th,
2007
Setting section 2 in place |
April 27th,
2007
Raising the roof |
| |
|
 |
 |
April 23th,
2007
Pouring the crush pad |
April 23th,
2007
Constructing roof support sections
on
completed building floor |
| |
|
 |
 |
April 19th,
2007
19 columns up in one day! |
April 19th,
2007
The crush pad is ready to pour |
| |
|
 |
 |
April 13th, 2007
First steel building parts arrive on pad |
April 19th,
2007
Six months after vineyard removal,
the first support column goes up. |
| |
|
 |
 |
April 13th, 2007
Making sure our floors are perfect!
|
April 13th, 2007
Office floor completed |
| |
|
 |
 |
April 13th, 2007
Completing
barrel room pour |
April 13th,
2007
Office floor ready to pour |
| |
|
 |
 |
April 4 , 2007
Dave & Jesus waterproofing the retaining wall |
| |
 |
 |
April 4 , 2007
It took a crew of 20 to pour the complex tank room floor |
| |
 |
 |
March 28, 2007
Pouring the warehouse floor |
| |
|
 |
 |
March 28, 2007
Septic System installation between the vines |
| |
|
 |
 |
March 8, 2007
Setting the trench drains in the tank room is precise work! |
| |
|
 |
 |
January 12th, 2007
Here we go! Pouring the Retaining Wall |
November 7th, 2006
Winterized & Ready to Begin Construction |
| |
|
 |
 |
October 24th, 2006
Groundbreaking Celebration |
October 24th, 2006
Popping the cork on our
own 2000 Meredith Cuvée |
| |
|
 |
 |
October 24th,
2006
Grading equipment
at work in the early morning fog |
October 24th,
2006
Does this photo
really need a caption? |
| |
|
 |
 |
October 19th, 2006
At the future site of Merry
Edwards Wines:
Coopersmith Vineyard |
October 19th, 2006
Clearing 2 acres of vineyard completed |
| |
|
 |
Our “virtual” winery: A
computerized illustration of the finished facility,
dropped into the existing landscape. |
|